By Matt Wiley

Although it may be holding up the completion of the Bruce B. Downs (BBD) Blvd. widening from Pebble Creek Blvd. in New Tampa south to Palm Springs Blvd. in Tampa Palms, the I-75 widening project between Fowler Ave. and S.R. 56 actually is ahead of schedule — unlike the widening of I-75 between S.R. 54 & S.R. 56.

Florida Department of Transportation (FDOT) District 7 spokesman John McShaffrey says that the $95-million project, which Prince Contracting, LLC, began in October 2011 to widen the 11.4-mile section of the interstate from four lanes to six lanes — and eight lanes near the interchanges — is cruising right along.

“The whole project is well ahead of schedule,” McShaffrey explains. “If you go by (Prince’s) schedule, they’re more than 500 days ahead. It looks very likely that they are going to finish that job early, depending on how much rain we get.”

And, part of that project includes the new, widened overpasses above BBD, which could now be open to traffic in both directions in late November to early December, McShaffrey says.

“After that happens, (Prince) will take the temporary bridge out and do all of the BBD widening underneath,” McShaffrey explains. “There’s a lot that can’t be done (for the widening of BBD) right now because of the location of the support structures for the existing temporary bridge.”