Businesses Feel Pinch Of BBD Widening

bbd-acrop
A rolling wall of dirt that obscures some businesses and discourages drivers from pulling in, say local business owners.

BBD ‘Segment A’ Construction Wearing Down Businesses, As Well As Drivers

Traffic is jammed, as a section of Bruce B. Downs (BBD) Blvd. just north of Bearss Ave. resembles a dusty obstacle course with barriers and tall mounds of rock and dirt everywhere. Despite a steady flow of cars, it’s a slow Friday afternoon amidst the cuts of beef and fish at the Land & Sea Market in the Oak Ramble Plaza shopping center.

Carlos Otero has managed Land & Sea for 16 years, and says that in the last few months, business has fallen as the road outside his shop remains under construction. He’s not alone, as neighboring business owners in the area have expressed frustration at the pace of the widening of BBD Segment A – from Bearss Ave. to Palm Springs Blvd. in Tampa Palms – from a divided four- and six-lane road to a divided eight-lane road.

bbd-aaa
Carlos Otero manages Land & Sea Market in the Oak Ramble Shopping Center, and is worried about the effects on BBD construction in the coming months, which are usually busy.

“The workers are not fast,’’ says Otero, who estimates his business is down 50 percent the past two months. “You come in every day, and it is the same. It doesn’t seem like there is any progress. And, people who come in, they say the same thing.”

Acropolis Greek Taverna general manager Tarek Armoush agrees.

“It’s definitely frustrating,’’ says Armoush, who helped open the New Tampa Acropolis location in the same Oak Ramble Plaza in 2007. “The biggest frustration is that I don’t feel like they have put the construction in (high gear). I see days where there is one worker out there, maybe two. It just seems they could speed this up.”

Segment A, which spans 3.5 miles and has a pricetag of about $60-million, is the third of a four-segment project that will ultimately, finally transform New Tampa’s congested main artery from four and six lanes into eight, all the way from Bearss Ave. to County Line Rd.

Segment A construction includes a 5-6 ft. sidewalk on the west wide of BBD, and a 10-ft.-wide multi-use path on the east side. Also, the southbound side of the small bridge that crosses over Cypress Creek (between the Landmark at Grayson Park apartments and Amberly Dr. in Tampa Palms) has been widened, and a new four-lane bridge on the northbound side of BBD has been constructed.

bbd-aaHillsborough’s Public Works Dept.’s project manager David Vogel says that while he understands your frustration, the perception that work is not being conducted as quickly as possible is wrong. Much of the work is done underground, he says — with utilities, electrical and water — and is not visible to the everyday passerby.

“There’s actually a lot going on,’’ he says, adding that Segment A — which was delayed from a spring 2017 finish to an August 2017 finish because of an elevation issue in one of the critical areas of construction — is smoothly moving forward.

That doesn’t mean the effects aren’t being felt, however. Businesses have about another year of construction in that area to look forward to, and Otero and others wonder how they will weather another year of roadwork.

Even successful businesses like Acropolis, Land & Sea and Mr. Dunderbak’s, also located in the Oak Ramble center, have seen changes in their bottom lines.

“We were down last month,’’ according to Mr. Dunderbak’s owner J.B. Ellis, “and we haven’t been down…ever.”

That’s significant for a business that has been at its current location since 2009, when it moved from the University Mall on Fowler Ave. The percentage loss may have been miniscule compared to what Mr. Dunderbak’s brings in yearly, but Ellis is concerned about a possible trend. A one-month loss is one thing, but multiply that by 11 or 12 months and it would leave a much bigger mark.

“The first half, I thought they did a great job,’’ Ellis says. “I watched them build that bridge in no time. I was thoroughly impressed. But, it doesn’t feel like much is being done these days.”

Ellis says there are still roads in and out of the Oak Ramble center, but they have changed to accommodate construction. You can’t turn left out of Oak Ramble, and if you turn right, it’s a one-mile drive up to Amberly Dr. before you can make a U-turn. Ellis says the entire area is one big car accident waiting to happen.

Changing travel patterns, the plethora of construction equipment and barriers and the congestion caused by it all is a deterrent to many customers who might otherwise stop. Currently, there is a winding 10-foot mound of rocks and dirt roadside obscuring Acropolis (see photo below) and other businesses up and down BBD from drivers. “Another year of this? Seriously?,’’ asks Ellis.

Rose O’Berry owns A Special Rose Florist n the other side of Bruce B. Downs Blvd. Like Carlos Otero, she says walk-in business is down 50 percent as construction makes it a hassle for customers to access their businesses.
Rose O’Berry owns A Special Rose Florist n the other side of Bruce B. Downs Blvd. Like Carlos Otero, she says walk-in business is down 50 percent as construction makes it a hassle for customers to access their businesses.

Across from BBD, Chevron gas station manager Danny Piguave said the construction has had a “lot of effect” on business.

Chevron was a Shell station before a massive overhaul that included new pumps and a redesigned store. However, for the last year, the gas station’s entrance has been a dirt road with barricades and sometimes feels like ground zero for all the construction, Piguave says.

“Somedays, it looks like there’s no way in,’’ he adds. And, summer rains often reduced the entrance to a muddy patch. “Who wants to drive over that?”

When the gas station was upgraded, Aguave said the expectation was that there would be an 18-20 percent increase in business. But, that number isn’t being close to being realized at the moment.

“It’s another year of this I’m worried about,’’ he says.

Rose O’Berry, whose A Special Rose florist shop is attached to the Chevron, says her walk-in business is down 50 percent. She does most of her sales through the internet these days. “We have to, there’s no choice,’’ she says.

O’Berry also says that customers are complaining, as getting out and then back into traffic is a chore many are just unwilling to endure. “I just sat in traffic for half-an-hour just leaving Tampa Palms,’’ one recently told her.

“It feels like they just keep digging right in front of us, like they have dug up the same area three times’’ O’Berry says. “It’s been like this almost a year now.”

Vogel says he doesn’t recall if that’s the case, but doesn’t doubt O’Berry. “That may be true,’’ he says. “You do utilities, then you do drainage work, then you have to dig back in for another utility. The underground work always looks like there’s no progress being made.” But, there is. While Vogel sympathizes with local businesses and drivers, he says there is no way to widen a road without creating a disturbance.

“We do everything we can to mitigate the effects, but can’t we eliminate them,’’ he says. “All we can ask is that they be patient, it will get better. Eventually, it will be easier for people to access their businesses.”

BBD Widening Enters Final Phase

bbd-roadLocal residents have been waiting more than 20 years for the main thoroughfare through New Tampa to be widened from a four- and six-lane divided roadway to an eight-lane divided roadway to relieve the area’s infamous traffic congestion. And, while it may be premature to say there’s a light at the end of the, well, Boulevard, local residents are a step closer to Bruce B. Downs (BBD) finally being “Bruce B. Done.”

Work on the last of the four segments of BBD widening finally began on Oct. 18, and is expected to conclude by the end of summer 2018. Prince Construction LLC’s finalization of Segment D, a 1.44-mile-long stretch between just south of Pebble Creek Dr. and County Line Rd., should conclude the long and sometimes arduous process of the major project that runs from just north of Bearss Ave. to the Pasco County line.

According to the county’s website, Segment D is a $24-milion project that is funded through the Public Works Transportation Capital Improvement Program (CIP) and was awarded $5 million from the Transportation Regional Incentive Program (TRIP) by the Florida Department of Transportation (FDOT). The segment will include a landscaped median, drainage improvements, pedestrian safety features, sidewalks, a multi-use path and an upgraded traffic signal system.

Segment A, which is still the most congested area of BBD and extends from Bearss Ave. to Palm Springs Blvd. in Tampa Palms (see previous page), is a $54-million project that should be finished around August 2017.

Segments B and C, which bracket the work that was done around the same time I-75 was widened, were considered the most difficult of the segments geographically, but they were finally  completed earlier this year.

bbd-nThe same night that work began on Segment D, the county held a pre-construction meeting in the Paul R. Wharton High auditorium about widening BBD. If you think New Tampa is tired of talking about the traffic on BBD, consider this: the county set up three stands showing the area of construction, but the meeting was attended by only a dozen or residents.

One of the more vocal participants wasn’t even a resident, but rather a bus driver for Wharton who expressed a number of concerns about the traffic flow in the morning and afternoon during construction. Cheryl Puelo, who lives in Thonotosassa but has driven a school bus for Wharton almost since the school opened, said long lines in the morning at the Oak Preserve Blvd. entrance are already an issue that construction needs to be careful not to exacerbate.

Hillsborough Public Works Department project manager David Vogel said that every effort will be made so as not to interfere with the three primary driveways in use at Wharton during peak times.

“We told the principal of the high school (Brad Woods) we will do everything we can to coordinate,’’ Vogel said. “We can’t completely eliminate any impacts, but we will try to limit them, with things like night and weekend work.”

Others in attendance wondered how the road work would affect the already congested areas in front of both Walmart and Wharton, and asked about additional traffic lights to help drivers pulling out from businesses along BBD.

One piece of good news – the left turn lane in front of the Walmart that causes so many issues with drivers suddenly swerving right to exit it will finally be corrected.

“The biggest (problem) is the amount of traffic in the corridor,’’ Vogel said. “There is drainage and power lines (that need to be repositioned and considered), and the staging and coordination for something like that is always a challenge. Power lines have to be moved. And traffic has to be shifted to get a 66-inch pipeline in there.”

And So It Begins…

As a result, Vogel warns that for the first year or so, travelers won’t see many changes happening in terms of the actual road. He estimates that the first 400 days (of the 685 estimated to complete the project) will be underground work. Travelers will first notice temporary pavement put in as traffic is shifted over to allow crews to dig and position the utilities and power and water lines.

“It’s an urban project, so you have utilities and things like that,’’ Vogel said. “The part people have the hardest time with is the underground work. You’re digging holes, you’re putting in pipe, water and sewer and all that stuff. No one sees any progress. All they see is they are digging here and, a month later, they are digging here again.”

Vogel said in many ways, the final segment will be the easiest. In Segment A, a bridge and four retention ponds needed to be built. Segments B and C also involved a bridge and working around construction at the busy BBD exits off I-75. By comparison, Segment D has far fewer challenges.

And, while it won’t mean drivers won’t become frustrated as the widening unfolds, Vogel said locals will start to see significant improvements by the end of next summer.

“There’s just a little bit of pain involved until you can get the cure,’’ he said.

I-75 Widening Delayed & Ahead Of Schedule, BBD ‘Segment A’ Coming Along

*IMG_0387By Matt Wiley

If you’ve been out driving on I-75 through the New Tampa and Wesley Chapel area, you’ve probably noticed some rough, uneven patches of roadway and a bunch of orange construction signs still standing. That’s because the widening project between E. Fowler Ave. in Temple Terrace to S.R. 56 still is not complete, although the project is still several months ahead of schedule.Continue reading

New Tampa Projects Top MPO’s Priority List As Cross Creek Blvd. Widening Wraps

Construction continues along Bruce B. Downs Blvd. in Tampa Palms, but it may not be the last of it for southern Tampa Palms, even after the current project wraps in 2017.
Construction continues along Bruce B. Downs Blvd. in Tampa Palms, one of the Hillsborough County MPO’s top transportation project priorities.

By Matt Wiley

Determining which transportation projects take priority over others is a complicated process debated by several local planning groups. Recently, the latest five-year transportation plan for all of Hillsborough County was approved and several ongoing and future New Tampa road projects sit on top of the Hillsborough County Metropolitan Planning Organization (MPO)’s 2015-19 Transportation Improvement Plan (TIP) priority list. One such project should even be completed as you’re reading this issue.Continue reading